Rezoning and Land Use Planning in Lee County
Lee County offers diverse development opportunities requiring a nuanced understanding of its specific regulatory landscape and growth management policies.
Who decides what
Recommending body
Deciding body
Application type
County Staff
Hearing Examiner — final
Conventional rezoning (REZ)
Hearing Examiner
Board of County Commissioners — final
Planned Development Rezoning (CPD, RPD, MPD, IPD, etc.)
Hearing Examiner
Hearing Examiner or BOCC, depending on the nature of the request
Planned Development Amendment
County Staff
Hearing Examiner — final
Special Exception (SEZ)
County Staff
Hearing Examiner — final
Variance (VAR)
Local Planning Agency (LPA) – Lee County Planning Board
Board of County Commissioners — final
Lee Plan Amendment (future land use text and map)
Typical Timeline
Planned development rezonings require two hearings — Hearing Examiner, then Board of County Commissioners — and typically run ten to fourteen months. Conventional rezonings, special exceptions, and variances end with the Hearing Examiner and move faster. Lee Plan amendments follow the state comprehensive plan schedule and require transmittal and adoption hearings and typically take a year or more.
What is Distinctive Here

Lee County's Hearing Examiner system is the most important procedural fact about entitlements here, and it is routinely misunderstood by consultants from outside the region. The Hearing Examiner is an independent office, staffed by attorneys board-certified in city, county and local government law, deliberately separated from the County Attorney and County Manager. Hearings are quasi-judicial and court-like, ex parte communication is prohibited, and the record based on expert testimony is what decides the case. A presentation that would satisfy a citizen board will not satisfy this forum.
Where that matters most is the split in authority. The Hearing Examiner issues final decisions on conventional rezonings, special exceptions, and variances. On planned development rezonings — which is most significant development in this county — the Hearing Examiner only recommends, and the Board of County Commissioners holds a second hearing to decide. At that second hearing new evidence is prohibited and public comment is limited to those who spoke before the Hearing Examiner. Everything you will need in front of the Board has to be in the record before the first hearing closes.
Lee County also requires community meetings in specific communities — Boca Grande, Captiva, Fort Myers Shores, Lehigh Acres, Matlacha, North Fort Myers, Page Park, Pine Island, Upper Captiva, and Olga — and in those places the neighborhood process is a code requirement, not a courtesy.
Work in this jurisdiction
2025 FPZA Award for Outstanding Redevelopment
Royal Palms Multifamily RPUD Zoning and Development
A 19.33-acre former mobile home park, severely damaged by Hurricane Ian and unsuitable for continued use, redeveloped as 376 apartment units using 40 percent bonus density together with greywater technology and affordable housing components.
This visionary project reimagines the former Royal Palm Village mobile home park into a resilient, sustainable, and community-driven multifamily development.